Wind farm Haven Gent Phase 2

Operational

The second Storm wind farm in the Port of Ghent features two extra wind turbines on the ArcelorMittal grounds. It has been be fully operational since Fall 2019 and produces enough renewable energy for approximately 6.500 families.

The second Storm wind farm in the Port of Ghent features two extra wind turbines on the ArcelorMittal grounds. It has been be fully operational since Fall 2019 and produces enough renewable energy for approximately 6.500 families.

On the map

In numbers

2
Number of turbines
3,6MW
Electrical power per turbine
130m
Tower height
200m
Tip height
140m
Rotor diameter
23.394MWh
Yearly energy production
Early 2018
Start of works
November 2019
Commissioning
356
Total number of participants
6.500
Yearly number of households provided with green energy